12 illustrated steps

Soffit and fascia

Follow the 12 illustrated steps in this soffit and fascia assembly.

  1. Step 1

    Open eave ready

    An open eave seen from below shows a bare wood fascia board and rafter tails above a wrapped wall, with pink insulation pressed against the roof deck in a section view.
    The roof and drip edge are finished. Under the eave we see rafter tails, the wood fascia board and the wrapped wall.
    Rafter tails and the bare wood fascia board
    Drip edge over the wood fascia board
    Cut view of insulation pressed against the roof deck
    Eave depth in the scene
    12 in
  2. Step 2

    Add the vent baffles

    Light blue channeled vent baffles sit between the rafters under the roof deck, with section views showing the open air space above the baffle and the insulation below it.
    We staple a vent baffle under the roof deck in every rafter bay. It keeps the air path open from soffit vent to attic.
    One vent baffle in every rafter bay
    Cut view of the open air path above the baffle, insulation below
    At least 1 in of open air under the roof deck
    Minimum air space under the roof deck
    1 in
  3. Step 3

    Nail up the receiving channels

    Seen from under the eave, the wall channel runs level with the fascia board bottom, with more channel at the gable end, with drawn tags and a slot drawing.
    We nail the wall channel level with the bottom of the fascia board, and more channels at the gable end.
    Cut view: wall channel level with the fascia bottom
    Nail centered in the channel slot, not tight
    Channel nails centered in the slots
  4. Step 4

    Measure and cut the panels

    A wood work table in front of a wrapped wall holds a long soffit panel and one short cut panel, with drawn marks for the opening and the 1/2 in shorter cut.
    We cut each panel 1/2 in shorter than the space from the wall to the fascia board, so it can move in heat and cold.
    Panel cut 1/2 in shorter than the opening
    Opening measured from the wall to the fascia board
    One full stock piece and a short cut panel
    Shorter than the wall to fascia opening
    1/2 in
    Room at each end
    1/4 in
  5. Step 5

    Slide in the first panel

    A soffit panel sits under the fascia board at the gable end of the eave, with close-ups of its end entering the wall channel and its edge in the gable end channel.
    We slide the first panel into the channels at the wall and the gable end, under the fascia board and square to the wall.
    Panel end sliding into the wall channel
    Panel end under the wood fascia board
    Panel edge seated in the gable end channel
    Panel width
    10 in
  6. Step 6

    Nail the first panel

    A ringed nail fastens the first soffit panel at its nailing edge under the fascia board, with close-ups of the nail head in the slot and a 1/4 in mark at the wall channel.
    We drive one nail through the slot in the nailing edge into the bottom of the fascia board, leaving the head a hair loose.
    Nail head in the slot under the fascia board
    Nail head left slightly loose in the slot
    1/4 in of room at the wall channel
    Room at the wall channel
    1/4 in
  7. Step 7

    Lock the panels along the eave

    Smooth soffit panels with V grooves run along the eave, with a drawn cut through the panel lock, a thin vent slit inside a groove and a long view of the face without holes.
    We hook each new panel into the lock of the last one and give it its own nail. The vent openings hide inside the grooves.
    Cut view of the lock joining two panels
    Thin vent slit inside a groove wall
    Smooth soffit face with no vent holes
  8. Step 8

    Run the soffit up the gable end

    From the gable corner, soffit panels run under the bare wood fascia to the end of the eave, with close-ups of panels up the gable end and aluminum on the corner face.
    We run the same panels up the gable end. Vinyl soffit runs to the end at the corner, with aluminum on outside faces only.
    Same panels run up the gable end
    Vinyl soffit runs to the end at the corner
    Panel ends in the channel on the gable wall
  9. Step 9

    Cover the eave fascia

    An aluminum cover now wraps the eave fascia above the soffit, with close-ups of it sliding up behind the drip edge, its bottom lip under the panel ends and a 1 in corner tab.
    We slide an aluminum cover up behind the drip edge. Its bottom lip covers the panel ends and a tab bends around the corner.
    Cover slides up behind the drip edge
    Bottom lip under the soffit panel ends
    1 in tab bent around the corner
    Corner tab
    1 in
    Bottom lip
    1 1/4 in
  10. Step 10

    Cover the gable board

    An aluminum gable cover runs up the rake behind the drip edge, with close-ups of it stopped just short of the corner tab, ready to lap over it, and its bottom lip under the gable end soffit.
    We put the gable cover on next. It laps over the 1 inch tab at the corner so water cannot get behind.
    Gable cover laps over the 1 in tab
    Bottom lip turned under the gable end soffit
    Gable cover runs up behind the drip edge
  11. Step 11

    Tack the trim nails

    Ringed trim nails sit in the bottom lip of the fascia cover, with close-ups of one nail held just below the lip, ready to be tacked in and a domed head.
    We tack painted trim nails through the bottom lip, snug but not tight.
    Trim nail held below the lip, ready to tack in
    Painted nail head, snug but not tight
    Trim nails snug but not tight
  12. Step 12

    Finished soffit and fascia

    The finished corner shows smooth soffit under aluminum fascia and gable covers, with a drawn blue arrow tracing intake air above the baffle and a drawing of the fascia bottom.
    Outside air enters through the hidden vents we installed, passes over the wall above the baffle and leaves at the ridge vent.
    Cut view of intake air above the baffle
    Smooth soffit with the vents out of sight
    Fascia under the drip edge