7 illustrated steps

Roof-to-wall flashing

Follow the 7 illustrated steps in this roof-to-wall flashing assembly.

  1. Step 1

    Leak barrier where the roof meets the wall

    A teal leak barrier strip runs up the side of a plywood roof where it meets a two story wall, and turns up onto the wall below the wrapped siding.
    Where the roof meets the wall, we press a leak barrier into the corner and turn it up the wall to seal the joint.
    Turned 6 in up the wall
    Laps over the eave leak barrier
    Eave: drip edge, gutter and end cap
    On the deck
    30 in
    Up the wall
    6 in
    GAF minimum up the wall
    5 in
  2. Step 2

    Underlayment to the wall

    White underlayment now covers the roof deck and runs to the edge of the wall, over the teal strip along the gutter edge.
    We cover the rest of the deck up to the wall with synthetic underlayment, overlapping the leak barrier so water runs over every lap.
    Runs tight to the wall
    Laps 3 in over the eave leak barrier
    Leak barrier stays up the wall
    Course width
    48 in
    Side lap
    3 in
    Lap over the eave barrier
    3 in
  3. Step 3

    Starter strip at the eave

    A starter strip now runs along the bottom edge of the roof by the gutter, next to the wall, with the underlayment above it.
    We run a starter strip along the eave to the wall, set slightly past the drip edge so water drips into the gutter.
    Starter runs to the wall
    End view: starter 1/2 in past the drip edge, over the gutter
    Butted end to end and nailed
    Overhang past the drip edge
    1/2 in
  4. Step 4

    Kickout flashing at the bottom row

    A small metal kickout flashing now sits at the bottom of the wall where the roof edge meets the gutter, over the starter strip.
    We set a kickout flashing at the bottom of the wall to turn roof water out into the gutter instead of down the wall.
    Kickout: 8 in by 5 in by 5 in, bent at 110 degrees
    Sealed end turns water into the gutter
    On the starter, at the lowest row
    Wall leg length
    8 in
    Wall leg height
    5 in
    Roof leg
    5 in
    Diverter angle
    110 degrees
  5. Step 5

    Step flashing woven with each shingle row

    Metal step flashing pieces now run up the roof beside the wall, woven between the courses of shingles.
    We give each row of shingles its own step flashing against the wall, each piece overlapping the one below to carry water onto the roof.
    One piece per row; the next row covers it
    Wall legs lap downhill, upper over lower
    One nail high on the roof leg, covered by the next piece
    Step flashing roof leg
    5 in
    Step flashing wall leg
    5 in
    Step flashing length
    8 in
    Minimum piece overlap
    2 in
  6. Step 6

    House wrap over the flashing legs (WRB)

    White house wrap now covers the wall above the metal step flashing, running down the wall over the flashing's upturned legs.
    We let the house wrap that is already on the wall down over the metal flashing, so water running down the wall stays outside.
    The same sheet of house wrap, let down over the flashing legs
    Wrap ends 2 in above the shingles, with the flashing legs behind it
    Kickout stays out in front, its wall leg under the wrap
    Wrap laps over the flashing wall legs, at least
    2 in
    Wrap stops above the shingles
    2 in
  7. Step 7

    Siding with 2 in roof clearance

    Siding now covers the wall above the roof, stopping a short distance above the shingles, with the gutter and kickout flashing at the bottom.
    We cut siding parallel to the roof, 2 in above the shingles as James Hardie requires, leaving only flashing in the gap.
    Kickout clears the siding
    2 in gap above the shingles
    Siding cut parallel to the roof
    Siding clearance to the roof
    2 in