15 illustrated steps

Roof installation

Follow the 15 illustrated steps in this roof installation assembly.

  1. Step 1

    Plywood roof deck (CDX)

    A bare plywood roof deck covers the main roof and the cross gable wing, with staggered sheet joints and rows of nails, above walls clad in siding.
    We sheathe the rafters with plywood sheets, staggering the joints, so every layer above is fastened to a solid, even deck.
    Sheet ends staggered; H-clips in the long joint
    Nails on the rafters at sheet ends and in the field
    Plumb fascia and vented soffit
    Plywood (CDX) thickness
    5/8 in
    Sheet width
    48 in
    Sheet length
    96 in
    End joint stagger
    48 in
    Panel gap
    1/8 in
    Rafter spacing
    16 in
  2. Step 2

    Drip edge along the eaves

    A thin metal drip edge runs along the bottom edge of the plywood deck on both roof sections.
    We nail aluminum drip edge along the bottom edges of the roof first, so the waterproof layers that follow can lap over the metal.
    End view: deck flange, hem, face and kick
    Two 10 ft lengths lap 2 in at the joint
    Runs to the gable corner, nailed along the run
    Aluminum thickness
    0.019 in
    Length
    10 ft
    Lap
    2 in
  3. Step 3

    Leak barrier along the eaves

    A teal self-adhering leak barrier strip covers the plywood along the bottom edge of the main roof and the cross gable wing.
    We roll waterproof GAF StormGuard leak barrier along the eaves, over the drip edge, where GAF calls for protection from ice dams.
    End view: the leak barrier lies on top of the eave drip edge
    Pieces lap 6 in at the ends
    Roll width
    36 in
    End lap
    6 in
    Wing sheet past the valley line
    6 in
  4. Step 4

    Valley leak barrier

    A teal leak barrier sheet now runs up the valley where the main roof meets the cross gable wing, over the strip along the bottom edge.
    We center a full roll of leak barrier in the valley, where two roof slopes send their water together.
    36 in roll centered in the valley
    Upper piece laps 6 in over the lower piece
    Roll width
    36 in
    Up each slope from the valley line
    18 in
    Lap
    6 in
  5. Step 5

    DeckArmor underlayment

    White roof underlayment with a repeating GAF pattern covers the main roof deck above the teal strip along the bottom edge.
    We cover the rest of the deck with GAF DeckArmor, a breathable underlayment that sheds water, each course lapping over the one below.
    Laps of 3 in and 6 in
    Stops 6 in short of the gable edge (rake)
    Laps 3 in over the eave barrier and 6 in onto the valley
    Course width
    48 in
    Side lap
    3 in
    End lap
    6 in
    Lap over the eave leak barrier
    3 in
    Lap onto the valley leak barrier
    6 in
    Setback from the rake
    6 in
  6. Step 6

    Leak barrier up the gable edges (rakes)

    A teal leak barrier strip now runs up the side edge of the main roof, over the underlayment and along the gable end.
    We run waterproof leak barrier up each gable edge, over the underlayment, because GAF lists rakes among the vulnerable leak areas of a roof.
    Rake leak barrier lies over the DeckArmor
    Upper piece laps 6 in over the lower piece
    At the corner it laps over the eave leak barrier
    Strip width
    36 in
    Over the DeckArmor
    30 in
    End lap
    6 in
  7. Step 7

    Drip edge up the gable edges (rakes)

    Metal drip edge now runs along the side edge and the lower edges of the roof, on top of the teal leak barrier strips.
    We nail matching drip edge up each gable edge, on top of the leak barrier, so the metal covers the edge of the membrane.
    Rake drip edge over the eave drip edge, face folded around the corner
    Two 10 ft lengths lap 2 in, upper over lower
    Nails between the ribs
    Length
    10 ft
    Lap
    2 in
    Face leg folded around the corner
    1 1/4 in
  8. Step 8

    Metal valley (W valley)

    A narrow metal sheet now runs down the center of the valley between the main roof and the cross gable wing.
    We lay a bent metal W valley over the leak barrier, nailed only along its outer edges so no nail goes through the channel.
    Foot: cut along both eaves, nailed at the edges only
    End view across the valley: the rib stands 1 in up
    Top: rib snipped, pressed flat and folded 2 in over the ridge
    Sheet width
    18 in
    Sheet length
    10 ft
    Flange
    8 in
    Rib leg
    1 in
    Nail in from the edge
    3/4 in
    Fold over the wing ridge
    2 in
  9. Step 9

    Leak barrier over the valley edges

    Teal leak barrier strips now run along both edges of the metal in the valley, with the metal ribs left open between them.
    We seal both edges of the valley metal and their nails under strips of leak barrier, leaving 3 in of bare metal beside the rib.
    One 18 in strip over each edge of the metal
    3 in of metal shows each side of the rib
    Strips cover the nails and run onto the DeckArmor
    Strip width
    18 in
    On the metal flange
    5 in
    Metal exposed each side of the rib
    3 in
  10. Step 10

    Starter shingles

    A row of starter shingles now runs along the bottom edge and the side edges of both roof sections.
    We lay GAF WeatherBlocker starter strips along every eave and rake, with factory sealant near the edge to help hold the first shingles in wind.
    Eave: the metal drip edge still shows under the starter
    Corner: the rake strip laps over the eave strip
    Rake: the same overhang, with metal showing below
    Half strip width
    8 1/2 in
    Strip length
    40 in
    Overhang past the drip edge nose
    1/2 in
    Minimum lap of rake strip over eave strip
    3 in
  11. Step 11

    Shingles: first rows

    The first rows of shingles now step up from the bottom edge of the main roof, while the rest of the deck is still bare underlayment.
    We lay shingles from the eave up, offsetting each row so joints do not line up, and nail where the next row covers.
    Top shingle: 4 nails, 1 1/2 in and 13 in from each end
    Each row shows 5 5/8 in, with a shadow line under each row
    Shingle length
    39 3/8 in
    Shingle height
    13 1/4 in
    Exposure
    5 5/8 in
    Row 2 trim
    6 in
    Row 3 trim
    11 in
    Row 4 trim
    17 in
    Nail line above the butt
    6 7/8 in
  12. Step 12

    Shingles: whole roof

    Shingles now cover the whole main roof and the cross gable wing, with the ridge still bare and the valley neatly cut.
    We shingle every slope. At the valley we cut the shingles back on a straight line, leaving an open metal channel for water.
    Open valley: shingles cut 3 in back from the rib on each side
    Wing: rows run parallel to the wing eave
    Top row: 4 nails per shingle, covered by the vent and caps
    Exposure
    5 5/8 in
    Valley metal left open each side of the rib
    3 in
    Top row nails below the peak
    3 1/2 in
  13. Step 13

    Ridge opening

    A narrow strip of the deck is open along the ridge of the shingled roof, with a small tool at one end of the opening.
    We saw a narrow opening along the main ridge so attic air can exhaust through the ridge vent that covers it next.
    Blue chalk line 1 5/8 in from the peak; the saw cuts along it
    End view: cut 1 5/8 in each side of the peak
    Looking down: the opening stops 16 in from the roof edge
    Opening each side of the peak
    1 5/8 in
    Maximum opening
    3 1/4 in
    Stop from the end wall
    6 in
    Stop from the roof edge
    16 in
    Saw blade
    7 1/4 in
  14. Step 14

    Ridge vent

    A ridge vent strip now runs along the top of the roof, with the shingles ending just below it.
    We cover the opening with a low ridge vent. It lets attic air out, and its filter resists weather, insects and leaves.
    One smooth, low top bent over the peak and nailed to the deck
    Outside wall stands in front of the air slots
    Roof edge: the vent runs to the end, closed end outward
    Section length
    4 ft
    Width
    11 1/2 in
    Cold weather joint gap
    1/8 in
    Minimum run past the opening
    6 in
    Ring shank nail
    3 in
  15. Step 15

    Ridge caps

    Ridge cap shingles now cover the ridge vent along the top of the roof and run down the cross gable ridge.
    We finish both ridges with two-layer ridge caps. On the main ridge we nail them through the vent, each cap covering the last cap's nails.
    Roof edge: 4 in starter piece under the first cap
    Last cap laid: 2 nails, which the next cap covers
    Wing ridge: a main roof shingle laps over the last cap
    Cap piece
    12 in
    Exposure
    8 in
    Starter depth
    4 in
    Starter length
    11 1/2 in
    Nails back from the exposed end
    9 in
    Nails in from the edge
    1 in
    Tongue under the main roof row
    2 1/2 in

See your own home like this