15 illustrated steps

Full-frame window replacement

Follow the 15 illustrated steps in this full-frame window replacement assembly.

  1. Step 1

    Window opening framed (rough opening)

    A tall window opening in a bare wood wall has a doubled header across the top and a rough sill on short supports at the bottom.
    We build new framing around the window opening, sized a little larger than the window so the window can sit level.
    Header from below: two 2x8 boards with a 1/2 in plywood spacer
    Rough sill on short supports (cripples), one under each end
    Plate, subfloor, rim and joist, sill plate, blue gasket
    Rough opening allowance
    1/2 in
    Rough opening width
    32 5/8 in
    Rough opening height
    62 1/2 in
    Framing spacing
    16 in
  2. Step 2

    Plywood sheathing

    Tan plywood sheathing now covers the wall around the tall window opening in four large sheets, with their stamped marks visible.
    We nail plywood sheathing over the framing in a few large sheets, each cut to fit around the opening.
    Cut flush: side framing and rough sill inside the opening
    Top corner: sheathing flush to the framing
    Sheet end joint on the framing, nailed on both sides
    Plywood thickness
    15/32 in
    Gap between sheets
    1/8 in
  3. Step 3

    House wrap cut and folded in

    White house wrap now covers the sheathing around the tall window opening, with the wrap cut and folded into the opening along the top and sides.
    We cover the sheathing with HardieWrap house wrap. At the opening we fold the sides and bottom inward and lift the top flap clear.
    Top flap folded up and taped, plain back showing
    Flaps folded in and stapled; the pan covers the corner next
    Upper sheet laps the lower by 6 in, seam taped
    Sheet lap
    6 in
    Head cut past corner
    9 in
  4. Step 4

    Sill pan flashing

    A flexible sill pan now lies in the bottom of the window opening, turned up at both ends over the white house wrap.
    We line the bottom of the opening with flexible flashing turned up both sides. It forms a pan so water at the sill drains out.
    Pan covers the whole sill and turns 6 in up the side
    Corner stretched and fanned onto the wall
    One piece across the sill
    Longer than opening width
    12 in
    Up each side
    6 in
    Roll width
    9 in
  5. Step 5

    Sealant where the flange will sit

    A thin bead of sealant now runs up both sides and across the top of the window opening, with the bottom left open above the sill pan.
    We run sealant up both sides and across the top of the opening where the flange will press in, leaving the bottom open to drain.
    Bead turns the top corner without a break
    Bead stops above the sill, so the bottom stays open
    One continuous bead across the top
    Bead size
    3/8 in
    Bead outside opening edge
    7/16 in
  6. Step 6

    Window set and leveled

    A double hung window with six panes in each sash now sits in the opening, its nailing flange flat against the wall.
    We press the new Vytex double hung window into the sealant and level it, with shims under the sill corners where they are needed.
    Flange pressed into the sealant, slots still empty
    Sill flange over the sill pan
    From inside: shim under the sill corner
    Window width
    32 1/8 in
    Window height
    62 in
  7. Step 7

    Nailing flange fastened

    Small round fastener heads now show along the nailing flange on all four sides of the window.
    We fasten the window to the wall through its nailing flange, one fastener in every other slot, on all four sides.
    Flange: fastener in every other slot
    Sill flange fastened too (Vytex step 9), over the pan
    Side flange: every other slot, up the whole side
  8. Step 8

    Side flashing tape (jamb)

    Flashing tape now covers both side edges of the window frame, running over the nailing flange and the house wrap.
    We seal each side flange of the window to the wall with flashing tape that runs past the sill flashing below and above the opening.
    4 in tape: 1 3/8 in on the flange, 2 5/8 in on the wall
    Runs 3 in past the sill flashing
    Runs 3 in above the opening
    Tape width
    4 in
    On the flange
    1 3/8 in
    On the wall
    2 5/8 in
    Past sill flashing
    3 in
    Above the opening
    3 in
  9. Step 9

    Top flashing tape (head)

    Flashing tape now also covers the top edge of the window frame, with the folded house wrap flap above it.
    We seal the top flange with flashing tape that laps over the side tapes. We never tape the bottom flange, so water can escape.
    Top tape over the 4 in side tape and 3 in past it
    One piece across the top
    Bottom flange not taped, so the pan can drain
    Past each jamb tape
    3 in
    Tape width
    4 in
  10. Step 10

    Exterior trim boards

    Trim boards now frame the window on all four sides, over the house wrap and the flashing tape.
    We frame the window with trim boards and seal the small joint between trim and window. The top board caps over the side boards.
    Top board caps over the side board
    Sill board fits between the side boards
    Sealant bead in the 1/8 in joint, all around the frame
    Trim face
    3 1/2 in
    Trim to window gap
    1/8 in
  11. Step 11

    Metal flashing over the top trim

    A narrow strip of metal head flashing now sits on top of the trim above the window, below the folded house wrap.
    We cap the top trim board with aluminum flashing, its lip throwing water clear of the trim. Next we fold the wrap flap over it.
    End dam: end of the flat top bent up 1/4 in
    Flashing ends 1/2 in past the end of the top board
    From the end: drip lip kicked out, hem folded flat
    Wall leg
    2 in
    Drip lip off trim face
    1/4 in
    Past each board end
    1/2 in
    End dam
    1/4 in
  12. Step 12

    House wrap flap folded down and taped

    The house wrap flap is now folded down over the metal head flashing, with tape along its edges, above the window trim.
    We fold the house wrap flap down over the metal flashing and tape both cuts, so water on the wrap runs out over the flashing.
    1 7/8 in seam tape from the flashing to the end of the cut
    Flap laps over the flashing leg
    Same on the other cut
    Seam tape width
    1 7/8 in
  13. Step 13

    Insulate the gap from inside

    A wall opening seen from the room side shows bare wood framing, a window in the opening, and a gap between the frame and the wood.
    From inside, we fill the small gap between the window frame and the wall framing with low expansion foam to insulate around the window.
    Top corner: foam in the gap all around
    Sill corner: foam along the sill gap too
    House wrap folded in over the framing; foam in the 1/4 in gap
    Gap each side
    1/4 in
  14. Step 14

    Siding fitted to the trim

    Siding now covers the wall around the window, ending against the trim on all four sides.
    We fit fiber cement siding around the window, leaving a narrow joint at the trim for sealant and an open gap above the metal flashing.
    1/4 in open gap above the flashing, not caulked
    1/8 in joint at the side trim, ready for sealant
    Plank notched under the sill trim
    Exposure
    7 in
    Joint at trim
    1/8 in
    Open gap above flashing
    1/4 in
    Minimum lap
    1 1/4 in
  15. Step 15

    Siding sealed to the trim

    A smooth bead of sealant, color matched to the siding, now closes the joint where the siding meets the trim at the sides and under the sill, with the gap above the head flashing left open.
    We seal the siding to the side and sill trim with color matched sealant. The gap above the metal flashing stays open to drain.
    Plank ends sealed to the side trim
    Sealed under the sill trim and around the corner
    Above the head flashing: gap left open, no sealant
    Joint at trim
    1/8 in
    Open gap above flashing
    1/4 in